Trimmingham Drive

  • Client:
  • Location:
  • Date:
  • Service:
  • Total Cost:
  • Completion Time:
  • Private Home Owner
  • Bury
  • Feb 2023
  • Extention
  • Circa £95k
  • 11 Weeks
Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.
JOB DETAILS
TIMELINE OF PROGRESS
  • Foundations (2 Weeks)
  • Brick/Block Work (5 Weeks)
  • Roof & Knock Through (8 Weeks)
  • Electrical & Plumbing (10 Weeks)
  • Plastering & Completion (11 Weeks)